Concrete Buying & Pour Planning Guide
Bags or ready-mix, what to confirm with your supplier, and how to plan the pour day.
Calculate concrete for slabs, footings and posts. See the cubic yards you need, compare bag quantities, and decide how to buy.
Measure the finished slab. Thickness is the depth of concrete, not including any gravel base.
You need about 1.48 cubic yards of concrete
No allowance added. Exact volume from your dimensions.
An optional allowance can help account for uneven excavation, minor measurement differences and handling losses. Use the quantity appropriate for your project and confirm order increments with your supplier.
Compare the quantity, handling effort and estimated cost before choosing how to buy.
Each product lists its own yield on the bag, and it depends on the mix. These are typical label yields for standard concrete mix: 40 lb ≈ 0.30 cu ft, 60 lb ≈ 0.45 cu ft, 80 lb ≈ 0.60 cu ft. Check your bag, or choose “From my bag” to use its exact yield.
Concrete estimate — CalcBrite Slab: 12 × 10 ft, 4 in thick → 1.48 yd³ Calculated volume: 1.48 yd³ (40.0 cu ft) Allowance: none Bags: 67 × 80 lb (5,360 lb) Ready-mix: 1.48 yd³ Quantity only. Confirm mix, minimums and delivery with your supplier. calcbrite.com/concrete-calculator/No account needed. The share link keeps your dimensions and choices, never prices or anything personal.
Concrete is sold by volume3. Multiply length × width × thickness, all in feet, to get cubic feet, then divide by 27 for cubic yards8. A 12 × 10 ft slab 4 inches thick is 12 × 10 × 0.333 = 40 cubic feet, or about 1.48 cubic yards. For round holes, the area of the circle (π × radius²) times the depth gives the volume of one hole: four 12-inch holes 36 inches deep come to 9.4 cubic feet, about 0.35 cubic yards.
It depends on the product. Typical label yields for standard concrete mix are about 0.30 cu ft for a 40 lb bag, 0.45 cu ft for 60 lb and 0.60 cu ft for 80 lb12, so one cubic yard (27 cu ft) is roughly 90, 60 or 45 bags. Specialty mixes yield differently: always check the bag.
Bags are easy to buy in small amounts and suit small pours, but every bag has to be carried, mixed and placed while the earlier batches are still workable. Ready-mix arrives mixed and can be placed in one pour, but suppliers may have minimum orders, short-load charges and access requirements5. Compare the bag count, the weight you’d handle, the help and equipment you have, and the prices you’re quoted.
The calculator shows the exact volume from your dimensions and adds nothing unless you choose an allowance. Small differences add up: the National Ready Mixed Concrete Association notes that a ⅛-inch difference in a 4-inch slab means a 3 percent shortage, and suggests ordering 4 to 10 percent more than the plan volume for waste, over-excavation and other contingencies43. The right amount depends on your site. Ask your supplier how they round orders and whether there’s a minimum load.
Confirm the mix and strength your project specifies, the dimensions on your plans, whether the truck can reach the pour or you need a pump or wheelbarrows, how long you have to unload, and the supplier’s minimum order and fees5. CalcBrite calculates quantity only: thickness, reinforcement, footing depth and permits come from your plans, local code or a qualified professional.
Multiply length × width × thickness in feet (thickness in inches ÷ 12). Divide cubic feet by 27 for cubic yards. 12 × 10 ft at 4 in is 40 cu ft, about 1.48 yd³.8
Divide the cubic feet by the yield on the bag, typically about 0.60 cu ft for an 80 lb bag, and round up. 40 cu ft ÷ 0.60 ≈ 67 bags.12
27. A cubic yard is a cube 3 ft on each side (3 × 3 × 3).8
Yes: add each pour and the calculator totals them. The total is for planning; separate pours may need different mixes, deliveries or pour days, so confirm with your supplier.
No. It shows the measured volume. You can add an optional allowance of 5%, 10% or a custom amount. The National Ready Mixed Concrete Association suggests ordering 4 to 10 percent more than the volume from plan dimensions, for waste, over-excavation and other contingencies.43
Yes. Choose Footing for continuous strip footings or Posts & Piers for round holes and tube forms.
Open “Compare my costs” and enter the price per cubic yard, delivery fee and any short-load fee your supplier quotes. CalcBrite doesn’t provide prices.5